On 23 November 2026, at the Cité internationale universitaire de Paris, the Ministry of the Economy presented the second edition of Choose France dedicated to French companies investing in the country. The press kit from Bercy (the French economy ministry) lists 273 projects carried by 253 companies, worth €42.5 billion. Digital ranks second among sectors, with 40 projects. The only digital infrastructure project quantified in billions in the document, the data centre joint venture between Orange and Morrison, was however made public on 27 July, and its documentation has not yet been signed.
81 new projects out of 273, with no mention to identify them
The document itself provides the key to reading the total. Of the 273 announcements, 192 were already known. The 81 projects presented as new represent nearly €14.9 billion, or 35% of the envelope. The remaining €27.6 billion correspond to investments made public earlier. In amount, the proportion has changed little in a year: according to the same document, the November 2025 edition counted 151 projects for €30.4 billion, including about thirty new projects for around €10 billion.
Two programmes dominate the total. Groupe ADP plans €9.5 billion for the overhaul of Paris-Charles-de-Gaulle and Paris-Orly airports, "subject to approval by the board of directors", the document specifies. RTE, the electricity transmission system operator, accounts for €8 billion, according to Reuters, which reported on 22 November the elements communicated by the Élysée. Together, they weigh €17.5 billion, more than the entire amount presented as new. At least part of these two programmes therefore falls under previous announcements.
The document does not say which. As of 24 November, the press kit posted online by Bercy classifies companies by region and describes some projects, but no sheet carries an explicit mention "new" or "already announced". The amount for RTE does not appear either, as the network operator has no project sheet.
Forty digital projects, eight quantified sheets
Digital goes from 28 projects in 2025 to 40 in 2026, behind energy and environmental transition (67 projects). Bercy publishes no amount by sector. The "digital sovereignty" chapter of the document describes eight projects, whose combined amounts reach about €3.3 billion. Orange alone represents €3 billion.
The seven other sheets range from €5 million to €175 million. Qonto announces €175 million and 300 hires by end-2027, after obtaining its credit institution licence. Calcore plans €110 million for a data centre in Normandy, Kiro a programme of over €17 million supported by France 2030, Eridanis about €10 million over three years. Then come three fundraisings of €5 to €9 million (Kwan-tek, NPco, Faactopi). The regional list cites other names in the sector, including Etix Everywhere, Eclairion, NumSpot, Probabl, Gradium, Quandela and Quobly, without description or amount in the document.
Orange and Morrison: 400 MW targeted, an exclusivity agreement at this stage
The heaviest project in the chapter was not born at the summit. The Orange press release dates from 27 July 2026 and announces the signing of an exclusivity agreement with the investment firm Morrison, with a view to creating a data centre joint venture based in France and co-controlled by the two partners. The text describes the operation in the conditional, and the Bercy document repeats the wording: the partnership "would constitute" a strategic investment.
Orange would contribute five data centres spread over four campuses (Chevilly-Larue, Aubervilliers, Chartres and Val-de-Reuil). The target capacity is 400 MW, "or nearly ten times the current capacity". The €3 billion programme would rely on "Orange's existing assets, Morrison's equity contribution and debt": the figure therefore mixes already built assets and capital to be raised. Orange Business would be the exclusive partner for marketing colocation and hosting offers.
The signing of the documentation "should take place by the end of 2026", subject in particular to consultation with employee representative bodies and regulatory approvals. Completion is expected in the first quarter of 2027. The government nonetheless staged the file on 23 November: the minister responsible for AI and Digital, Anne Le Hénanff, visited that day Orange's data centre in Amilly, near Chartres, where four new rooms have been added, two of which are already filled, reports L'Écho Républicain.
Calcore and Etix Everywhere, the day's announcements in data centres
The second data centre in the document is of a different size. Calcore announces €110 million for a "high-intensity" site in Normandy, powered by a long-term supply contract from a neighbouring biomass plant. The document gives neither capacity nor timeline. Capital mentions 20 MW and delivery expected in early 2028.
A third project was quantified on the day by its promoter. In a press release reproduced by DCmag, Etix Everywhere announces €100 million to add 12 MW to its edge data centres in Île-de-France, Hauts-de-France and Occitanie. The operator specifies that €50 million come from a refinancing announced in September 2025, the rest being contributed in equity. Half of the amount had therefore already been made public.
On the usage side, Kiro launches OPTIMABIO with AP-HM (Marseille public hospitals), Hospices Civils de Lyon and Limoges University Hospital, to develop AI to assist in prescribing biological tests. Crédit Agricole announces it has selected the start-up Prisme.ai as technology partner to deploy AI agents connected to its information system, with no amount communicated.
400 MW for Orange, 3.1 GW for SoftBank's first phase
The comparison with the international edition of 1 June 2026 gives the scale. At Versailles, €93 billion had been displayed, including €45 billion firm for the first phase of SoftBank in Hauts-de-France, i.e. 3.1 GW by 2031. The 400 MW targeted by Orange and Morrison represent about one eighth of that tranche alone. The 23 November document recalls the order of magnitude: more than €180 billion of investments in data centres claimed since the AI Action Summit of February 2025, where €109 billion had been announced for AI, and the 2025 and 2026 editions of Choose France. It also indicates that projects under development have secured 25 GW of electrical capacity from RTE.
The comparison also holds for the needs that the executive itself formulates. In a video published on 15 November, Emmanuel Macron said he wanted to "secure one gigawatt before the end of 2028", computing capacity that he says should allow Mistral AI to remain in the competition, i.e. "about €50 billion over five years", according to the transcript given by Next. Mistral AI does not appear in the list of companies published by Bercy.
The showcase of 23 November describes a fairly clear division of roles. According to the announcements recorded since February 2025, the capital financing computing power in France comes mainly from abroad, including in the Orange project, backed by an asset manager founded in New Zealand. French companies mainly provide sites, existing assets and use cases. For a buyer of hosting capacity or trusted cloud, the data centre projects quantified on this occasion number three. Only one exceeds one hundred megawatts, and it dates from July.
End 2026, early 2027, early 2028: the timeline of announced projects
The nearest deadline is that of Orange and Morrison, who plan to sign before the end of the year. ADP awaits for its €9.5 billion the green light from its board of directors and, according to Capital, the signing of its regulatory contract with the State. Delivery of Calcore's Normandy site is expected in early 2028, again according to Capital. As of 24 November, the Bercy document still does not allow isolating the 81 new projects.